Wisconsin Statutes (Last Updated: January 10, 2017) |
Chapter 893. Limitations Of Commencement Of Actions And Proceedings; Procedure For Claims Against Governmental Units |
SubChapter V. TORT ACTIONS |
Section 893.59. Actions concerning damage to highway or railroad grade.
Latest version.
- An action under s. 88.87 (3) (b) to recover damages to a highway or railroad grade shall be commenced within 90 days after the alleged damage occurred or be barred.
1979 c. 323
.
Judicial Council Committee's Note, 1979:
This section has been created to place into ch. 893 the statute of limitations for an action to recover damages to a highway or railroad grade. (See note following s. 88.87 (3) (b)). [Bill 326-A]